Friday, April 11, 2014

We Were Not One and Done

By Marvin Kemp, AIA, CSI, CDT


This is the third in a series of blogs that will recount/investigate a collaboration exercise undertaken by a large and diverse project team involved in a large and complicated biomedical research building. I intentionally do not mention the project, client or team members because their names are not germane to the discussion and because I did not ask their permission to use their names. 

As the title implies, we met again for our team collaboration session. This session was held six weeks after the original session and was shorter than the initial full day affair. The group met for just three hours in the afternoon. We had targeted to meet again in two months, but the moderator and the CM’s project manager looked at the project status and the calendar and decided to shorten the duration between meetings. This session was held on November 21, exactly one week before Thanksgiving and three working days before the design development cost estimates were due to the entire team. This appeared to be a critical juncture in the project, so we reconvened. 

Though this session had some of the same players as the initial, it was intended to be just the project manager level folks. We  were asked to grapple with the four problems that were identified by the larger group as being the most critical: 
  • User Changes
  • Coordination
  • Decision Making/Communication
  • Design-Assist Procurement/Funding Impact
The idea being that this PM group would discuss the problems, create solutions and measurements and then report to the full group on January 7, 2014. The lead moderator from the original workshop, was back but his assistant moderator was not. We had the senior PM from the construction manager, the main PM from the owner (but not his newly assigned assistant PM), the PM’s from the four design-assist contractors (concrete, glazing, electrical and HVAC/plumbing), the assistant PM from the architect of record and myself, the PM for the associate architect. We also had senior managers, if not PM’s, from the primary engineering firms. This time, we were joined by the Director of Operations from the school that will be the primary tenant of the building. I’m not sure why he was not at the original session, but it was good that he was included for this session because when we tackled “user changes,” he represents the user.

The moderator brought the Ops Director up to speed on what happened in the first session. The group then reviewed the four problems and discussed in what order they should be tackled. I offered that this group is not in a position to solve the "Design-Assist Procurement/Funding Impact" issue because none of us are with the university’s procurement department and none of us are state legislators, so our possible impacts on that issue are minimal if they exist at all. The idea that this university is new to the concept of design-assist and is somewhat distrustful of the process was expressed. After some discussion, we all agreed that the best way to show the university that design-assist works is to perform well as team.

When considering the procurement process as a whole, regardless of our individual role in it, our moderator cautioned us to not escalate emotion. Remember that the moderator is an employee of the CM but is also a psychologist. Several attendees expressed frustration with the procurement process. The design-assist contractors are under contract for “pre-construction” services only and have no contractual guarantee of being awarded the construction contract. The moderator said a real or perceived lack of trust exhibited by the university is not personal and should not be taken personally. All participants must control their frustration and be as calm and level headed as possible when dealing with the team.

With the expressed goal of discussing issues and creating measurements to gauge success, an order of discussion was presented that the group might use to reach that goal:
  • Defining the problem should be first. The team must consider the current problem and what the teams aspires for the outcome to that problem to be.
  • The team should next analyze how the team is currently performing and what might a Team Oriented Solution (T.O.S.) look like.
  • Performance improvement will be considered next or what is the agreed upon solution to the problem.
  • Patterned performance must be discussed and used to determine if the Aspirational Goal, as defined by the team, is actually achievable.

Considering these ideas in order might lead the team to the expected solutions to the four problems and how they might be measured to gauge team success. To be fair, the group did not expressly follow that order of discussion in this session. The team very quickly identified problems and analyzed current performance, but fell short in how to improve performance or discussion of aspirational goals.

To better focus the group and because the Ops Director had to leave early for another meeting, the group decided to tackle the problem of User Changes. Unfortunately, the process quickly broke down into a complaining session, which the moderator let continue for too long. Frustration was expressed with changes that cost the entire team in terms of design and engineering time. Some specific examples from this project were given that all agreed were troublesome. The moderator pointed out that if any individual is frustrated, then so are other members of the team. None of us are alone in the project so none of us are alone in our frustrations. It was noted that an aspirational goal could be doing cost reduction exercises without redesign of major systems and components which would cost the entire team more money with design and engineering effort.

It became apparent that the group was grappling with two different types of changes. All realize that minor changes happen at the end of large and complicated projects. This particular facility is intended to be used to recruit new faculty researchers, so once those faculty are on board, minor changes should be expected: electrical outlet moves, additional IT drops, etc.

The PM for the CM noted that the changes the team is currently encountering are semi-normal. Again, this is a very large and incredibly complicated building being built in a dense urban environment in an existing campus context. The myriad of players from the university side each come with their own thoughts, opinions and ideas on the best direction of the project. Change is inevitable in that environment, but the team must not get too frustrated and must deal with these changes as judiciously as possible. Finishing this blog post over four months after this meeting, I'm remembering that many of the frustrations and thoughts expressed came from the construction team, not the design team. While the design team was frustrated as well, I think designers are more used to these types of systemic changes during large projects with sophisticated clients.

It became apparent that the team was making a distinction between project requirements and actual changes. If the team does not meet a project requirement, a comment made during a submission review is generated that may cause a change to the documentation, but that is not a true change. The team merely missed a project requirement. There are some actual owner or user driven changes to the project that may cause the team to go in a completely different direction. Those are the types of changes that are most troublesome to those present.

It was suggested that a few items need to be defined by the team moving forward. The client should be given what they want and need, which is why this team was hired in the first place! This takes on a number of different ideas as there are university standards to meet as well as preferences on individuals who will work in, maintain and use the building. Sometimes these will conflict, but our job as professionals is to help the university work through those conflicting ideas reach the best solution.

While working to make sure the team gives the client what they want, we must all work to minimize costs and impacts to schedule. We are all under contract for a scope of work, schedule duration and fee or guaranteed maximum price. When the university asks for something that we believe the project cannot afford, we need to raise the flag for further discussion of that item. But above all, the team must be fair to all parties. Team members must avoid finger pointing and work together to reach the ultimate goal.

Ways to analyze the performance of the team against the coming changes was discussed, but the team wasn’t really focused on that yet. I suspect that focus will come only when faced with substantial changes, user directed or otherwise. We talked about ways to ensure that each of us works to match the design to the budget. We also discussed the sequencing of the fit-out of floors to maximize efficiency of the construction team and not the whim of the university. That means the construction team should work as efficiently as possible and not let the university dictate what floors are fit-out when, unless absolutely necessary. Some team members have worked on projects where a schedule for fit-out was stymied because the client was considering a particular tenant for a particular space. This team should stay the course for efficiency until that becomes an untenable solution.

Some metrics for issue tracking that are easily measurable were discussed and some durations agreed to. Suffice to say, that those in attendance agreed to quicker turn around times for issuance of change documentation, pricing and review and approval of pricing than is typical. The problem being, several members of the procurement team were absent and so the success of these metrics lies with folks who did not agree to these durations.

Finally, the next meeting was discussed. The idea of convening a smaller team to grapple with the issue of coordination was discussed. This would involve members of the A/E team and the MEP design-assist contractors but no decisions were reached. I think most realized this meeting was more venting than substance and with the holidays approaching, no one was willing to commit to a date. All  had January 7, 2014 as a hold on their calendars so it was decided that would remain as the next meeting. The agenda for that session would revolve around what happens during the DD pricing, reconciliation and value engineering/cost reduction exercises.

The Moderator gave a closing shot: give other teammates the benefit of the doubt. I think that’s something that most teams should do.

Friday, February 21, 2014

Mentoring Opportunity

This blog post comes to us from the School of Architecture and Planning at Morgan State University in Baltimore, MD. Professor Sanjit Roy is seeking professionals to help with his course "The Integrated Intelligent Detail." I've participated in this program in the past and find it to be a great way to meet the next generation of architects and be involved in their education. Please consider taking some time to help this fantastic students.


SCHOOL OF ARCHITECTURE AND PLANNING
MORGAN STATE UNIVERSITY
February 20, 2014

Whether you are a veteran mentor for "Architecture at Morgan", or brand new, I hope you will consider this opportunity to work with our graduate students of architecture.

Architecture at Morgan offers an innovative graduate-level course developed with the support of an NCARB grant known as: "ARCH.541: "The Integrated Intelligent Detail."

Would you be interested in mentoring a student in this course? The course runs from January to May, and the course requires students to investigate architectural detailing by working with a practicing architect as a mentor. The mentor contact with students involves three campus visits, and one or two meetings at your office.

This year the focus will be on the exterior envelope, including at least one fenestration detail. The participating mentor selects a project from their office with an interesting detail (built or proposed). The detail should present some challenges for alternative study by the student. Your student will create a BIM model of the detail, and then transform the detail using their research, design and BIM skills.

If you are able to serve a mentor you will work with 1-2 students guiding them as they develop a wall section/ detail for one of your current projects. You will be presenting the project t the students on either 25 Feb or 4 march, whichever date is convenient for you. Subsequently the students will meet with you at your office as they develop the details under your supervision.

The four on-campus dates that involve the mentors are:

1. Introduction of your architectural project to the class: on one of the following dates:

     a. Tuesday, February 25: 7:00 pm to 8:00 pm (one hour) OR

     b. Tuesday, March 4: 7:00 pm to 8:00 pm (one hour)

2. Tuesday, April 1: individual desk critique between 6:00 pm to 8:00 pm with your student mentee/s (allow about one hour)

3. Tuesday, April 22: individual desk critique between 6:00 pm to 8:00 pm with your student mentee/s (allow about one hour)

4. Tuesday, May 13: 6:30 pm to 8:30 pm FINAL REVIEW OF ALL STUDENT WORK (two hours) hosted at an Architecture office.

Thank you,

Sanjit Roy
Assistant Professor
School of Architecture & Planning
sanjit.roy@morgan.edu
443-228-8777

Friday, February 14, 2014

Ralph Liebing, RA, CSI, CDT

It is with great sadness that we announce the passing of Ralph Liebing, RA, CSI, CDT, an occasional contributor to this blog. Ralph's weekly per-SPEC-tives email newsletter was welcomed reading in my inbox each Wednesday morning.

Ralph died on February 9, 2014, leaving behind a wife, a daughter, a son and a granddaughter.

Tom Hellmann, AIA, Senior Vice President and Director of Architecture and Interior Design at Hixson Architecture, Engineering and Interiors said, "He was a great associate and even better man." Hear, hear. Ralph's intelligence, humor and home-spun wisdom will be missed by all who knew him. There is a giant hole in construction knowledge left by his passing.

Here is a link to his obituary and final arrangements. http://www.boltonandlunsford.com/obituaries


Wednesday, January 22, 2014

Submittals and The Client

by Ralph Liebing, RA, CSI, CDT
 
This post was borrowed from Ralph's weekly per-SPEC-tives email column. If you don't get this weekly writing on all things CSI and specifications, contact Ralph. I'm sure he'll be happy to add you to the distribution!
 

The title seems to indicate a rather strange and innocuous discussion. How many clients really care about submittals on their construction projects? Some will be quite interested; others will take little if any interest.

Many clients still see the submittal as the verification of what they will receive on their project—a “checks and balances” ensuring the true value received for dollar spent. Some see the submittal as the record of what is placed, for future reference, maintenance and replacement or trouble shooting. This of course, really is part and parcel of the Operating and Maintenance Manuals required on most projects.

Well, a big part of the answer may lie in the adverse impact of submittals when they disrupt the project schedule, and completion of the project. Yet there are other considerations. Some people has professed that submittals are useless, needless and obsolete. Is that true? Or is there a valid and proper place for submittals—properly requested, produced, processed, and utilized?

There is need to address several issues with the Owner, so there is full understanding of all circumstances surrounding submittals;

- Submittals will be requested ONLY to ensure that the Contractor[s] understand the requirements of the contract;

- Only a minimum number of submittals will be required;

- Requests will only be required for those submittals containing crucial information;

- The Contractor is responsible for the “means and methods of construction”  and is therefore the primary reviewer of submittals and their  compliance with the contract documents; erroneous, incomplete, and non-compliant submittals are to be returned to the preparer by the CONTRACTOR [all in accord with AIA A201, General Conditions of the Construction Contract];

- The Contractor is to review all submittals, check for errors, and stamp them with an approval stamp, PRIOR to submitting them to the design professionals [complies with A201];

- The design professionals ARE NOT responsible for an extensive review, not  for any information other than pointing out errors-- NOT correcting them [in accord with A201];

- Reviewed submittals will be returned in a prompt manner;

- Submittals sent to the design professionals without proper Contractor review and approval, will be DISCARDED/Returned with no further action [complies with A201];

- Any schedule disruption[s] attributable to faulty processing of submittals accrue to the Contractor [NOT the design professionals].

A conversation, with the client, on this topic is most important--and strongly urged and advised. It lays the groundwork for the procedures to be followed on the project that will ensure compliance with the project requirements and will give the full value of the work to the client. That context and conversation falls within the purview of the design professionals.

The Contractor may well have a very different “take” on submittals and the whole of the process. AIA Document A201, however, makes the submittals program and process quite clear and directed. It delineates the responsibilities of the various parties, and denotes a very specific progression of preparation, processing, review and approval—by several parties and with certain specific guidelines.

It is most important that the client be aware of these provisions so the work of the process will not be a surprise or an irritant to the client. Being made fully aware of the reason for, the background of, and the inner-working of the process is important, not so much in the minute details, as in the overall value and correct operation.

The submittals program is in place for good reason, and is time tested in the results it produces. Obviously, it is wrong to obviate or ignore this program for any reason or changed condition in a project. Of course, the client does have the right to pursue the project as seen fit-- hopefully this determination does not involve elimination of this clearly directed and helpful process.

Its value directly contributes not only to project success, but to value given to the client!

Saturday, November 9, 2013

Building a Highly Collaborative Team, Part 2

by Marvin Kemp, AIA, CSI, CDT

This is Part 2 of a blog about a collaborative team-building event I attended on October 8, 2013. Please read this post for the opening thoughts and action that occurred in the morning on the day of the event. This post will continue with what occurred following lunch.

The afternoon was spent in both small group discussions and large group discussion combined with reporting on the small group work and reaching consensus in the large group discussions. The afternoon opened with a large group discussion of the desired team working environment. The CM is hoping to build a true "co-location" environment where CM staff, design assist contractors and architects and engineers all work together in the same space. The problem is that the A/E contracts do not envision that level of effort until construction starts and I do not believe the CM has configured their co-location space with the infrastructure necessary to make that level of involvement available and efficient. Providing desks, wifi and coffee does not equal a successful co-location space. Moreover, contracts must be in place to ensure all parties understand their involvement, equally assess and accept risk and professional licensing concerns are eased.

At the collaboration event, we discussed behaviors that contribute to a healthy and collaborative working environment. The moderator was careful to call them "behaviors" to keep the conversation general enough to be useful and to differentiate immediate actions from long term behaviors. Things like bringing enthusiasm and cheerfulness, truthfulness, listening, consistency and accountability were discussed. Additionally, all parties must be respectful of each other but mindful of the delivery method to avoid honesty that is too brutal and might become hurtful. Team members should also come to discussions with solutions and not just problems.

The environment all would like to see has give and take in all situations. The "I win, you lose" type of attitude is not welcome nor healthy to the team. Members should be assertive with regards to their thoughts and ideas but not too aggressive. At the end of the day, the team should have fun and be "jocular not jugular:" all should watch out for sarcasm.

Confidentiality is also of critical importance. What is said in the room and among the team must stay in the room and among the team. That's why I'm being careful in authoring this blog. I want to describe the discussions, but not call people out or relay their attitudes or frames of mind. Twice, the moderator went around the room and asked if each team member, individually, accepted the idea of confidentiality. He waited for each member to verbally acknowledge their acceptance, similar to the flight attendant waiting for verbal acknowledgement from someone sitting in the exit row of a plane.  All of these behaviors were noted on flip charts and then pinned to the wall for all to review during the rest of the session and beyond.

Similarly, the team discussed behaviors that indicate regression or the team moving away from collaboration and returning to how things were in a non-collaborative environment. Team members not making meetings and missing deadlines indicate the metrics used to measure team success are trending in the wrong direction. If team members begin to suspend trust and poorly communicate or begin to point fingers, the team is regressing in their behaviors.  If there is an absence of fun and if team members avoid one another and frequently pull out contracts to review their scope, the team may be regressing. Understanding unhealthy behaviors is just as important as understanding the healthy behaviors teams should engage in so that all can embrace the healthy and avoid the unhealthy.

The first small group session was spent identifying current or anticipated issues the project team is facing or may face. The moderators split us into groups, making sure the groups were sufficiently diverse. For example, the first group I was in contained one engineer, two members of the owner's group, one member of the CM group and two design assist contractors but from different firms. There were three groups and three architects in the meeting, so we were split up in all groupings.

As our group discussion began, we tried to move beyond the usual issues of "budget," "schedule," and "quality" broad picture statements, although each of those ideas appeared in the overall discussion of the issues facing our project. We tried to get more specific to the nature of this project and the culture that has already begun to take form. Concern was expressed over the protracted funding schedule from the legislature, concern over the contractual arrangements of the design assist contractors and coordination of design and construction efforts by the A/E team, design assist team and CM staff.

Not so shocking, all three teams identified the same issues. Not shocking because the groups were painstakingly organized to maximize the interaction among all team members. Each team contained members of the A/E team, owner's team, CM staff and design assist contractors. Once you start to think beyond the usual or generic problems that all projects face and get into the nuts and bolts of the project at hand, I would expect all three teams to identify similar issues. Sure the wording was slightly different and they were in slightly different order but they were essentially the same issues.

Once we returned to the large group setting, each smaller group presented their thoughts and the rest of the team was allowed to ask questions.  As there was much consensus on the issues, the only questions were clarification of thought and terminology. The groups presented their thoughts on flip-chart pages that were pinned to the wall. This made locating commonalities easy: the moderators used red markers to circle or place asterisks next to common themes on the group pages.

At this point, the groups were shuffled and the discussion continued with the idea of prioritizing the top three to five issues and beginning to think about how to address each of the top three issues. This session was not as successful as the first for several reasons. Many of us chose to take a break for rest rooms and phone calls so the sessions were a bit late starting. Next, the groups were interchanged, so their members had some ramp up time, same as in the first break out sessions. Lastly, the prioritization discussions required more discussion than the issue listing so the session was more about finesse and than brain-dumping, as the first session had been.

This time, each group had a slightly different priority listing but three rose to the top. Coordination between A/E and design assist contractors, the protracted funding schedule and the contractual arrangements of the design assist contractors were clearly on everyone's mind. The initial solutions offered were all over the board and not clearly defined. The questions were more numerous and generally focused on specific ideas related to proposed solutions.

My group for this second break out included two senior members of the owner's team, the project executive from the CM, one design engineer and several members from various design assist contractors. While the project exec from the CM was vocal, the senior owners were not. I think they were trying to listen and learn. I bring up the group make up because of what happened in the third break out session. 

The moderator wanted the third session to feature the same groups as the second session. However, the most senior members of the architect of record, CM and owners team broke out into a separate session to discuss a decision making matrix thus leaving my team short three members. The remaining members split up and joined the other two groups to discuss real solutions to the top three issues. This proved to be a good start which left several action items for the owner, CM and A/E. I don't think the moderators expected concrete decisions to come out of this session as they were not surprised that we left with action items.

The discussion of the decision making matrix was interesting on two levels. The matrix was set up with five levels. Many of the people listed on the matrix were in the room and did not seem to agree with their slotting in the levels, even though those slots were set by senior project staff and in some cases, the person’s employer. The Level I slot is for the most senior, executive level people in each organization. Level II is reserved for the project manager level people and Level III for one step below that. The second thing that made this discussion interesting is, to my way of thinking and considering my project and team knowledge, Levels IV and V have no decision making ability: they are too far down the chain and quite frankly, not given the authority by their respective firms. This is evidenced by the owner and CM groups leaving these levels blank in their columns. Only the A/E team firms and design assist contractors had names in these slots.

I’m not sure what will become of this decision making matrix. It was stated that all decisions should be made at Level II and Level III, but the culture has already been set that this will not occur. The folks listed in Level I are too powerful and too entrenched in the process. The culture has already been set that these folks are the ultimate decision makers and they frequently insert themselves into decisions that could be made at a lower level. I am a strong believer in the power of project or corporate culture. Once a cultural moray, whether positive or negative, has been set on a project, it is incredibly difficult to break it. An example is meeting culture: if the meetings are allowed to start late, few will arrive on time as they know the meeting will not start on time.

The session came to a close with a discussion of next steps. The dominate view of partnering sessions in the introductions of the morning was that the “one and done” events do not work. Either immediately or over time, the participants return to their unhealthy behaviors. All team members need to be reminded of the importance of team work and collaboration. It was agreed that for follow up meetings, monthly was too often and quarterly might be too infrequent. It was decided that the team will reconvene every two months across the next six months, which are critical months in the overall project schedule. After the first six months, the meetings will be held quarterly. The follow-up meetings will be shorter: probably three to four hours initially and then maybe only two hours as time goes on.

I took a couple of things away from this day. At some point, someone from the contracting team asked about integrating additional team members into the collaborative environment. This session included all key members of the A/E team, owner’s team and CM team but only four of the trade contractors who will actually be contracted to build the building. What happens when the masons and other skin contractors as well as the interior fit-out and finish contractors join the team? That was the parting shot of the whole event that was left unanswered. Some noted, and I agree with this, that the behavior model we created starts at top of each firm and filters down through all team members. If the leaders can maintain the collaborative spirit, the rest of the team will fall in line.

The quote of the day came from the PM for the architect of record. He said, “this is a large, complex project. You either run away from it or you run to it. Today, we all agreed to run to it.” I hope that is the case. Only time will tell.

Wednesday, October 23, 2013

Building a Highly Collaborative Team, Part 1

By Marvin Kemp, AIA, CSI, CDT

On Tuesday, October 8, 2013, I spent all day in a partnering or team building event for a large biomedical research project I'm involved in. I wrote a few quick paragraphs before the event started bemoaning the possibility of wasting a day in "touchy-feely" type discussions with equally uncomfortable construction professionals. As the event wore on, I was pleasantly surprised by the quality of the program and the caliber of the moderators. For those who follow me on Twitter (@BaltoCSI), you've seen many tweets lately related to ideas that came out of this session and there are more to come. However, I felt that I should expand beyond 140 characters and give a more comprehensive description of the event and my thoughts on it. I wrote the whole post at once, but will split it into two parts as it became quite lengthy!

Construction projects of any size are not easy. That is part of what appeals to me about my profession and our industry. I focus primarily on projects at institutions of higher education and research or teaching laboratories, at that. At any given time during the design phases on projects I’m involved in, there may be six or more architects, 12 or more engineers and other consultants and as many as 20 or more owners personnel involved in the project. Once under construction, the project team can balloon to 10 members of the contractor’s team, 50 or more workers on site and untold numbers of people involved in the raw material extraction, product manufacture and distribution of materials and equipment to the site. With all of those people, each with a small part and each with their own agenda, the complexity of even the smallest project can be enormous.

The particular project I'm currently involved in is a 400,000 GSF, $218M behemoth. The A/E team features three different architecture firms plus a laboratory design firm, five primary engineering firms and six more specialty consulting firms with close to 50 design professionals engaged in the design and production of contract documents. Our internal team coordination meetings routinely feature 15 or more people in the room and another six to eight on conference call. Right now, at design development, the drawing set is four volumes of over 200 drawing sheets each and two volumes of specifications at about 500 pages each. My firm is the associate architect, working closely with the architect of record and the rest of the team. I am our firm's project manager and assistant PM for the whole team.

The owner has retained the services of a construction management firm to perform both pre-construction and construction management services, including managing a design-assist process. For those unfamiliar with that delivery method, the CM has contracted with sub-contractors to assist in the design of the concrete structure, glazing and metal panel systems and HVAC, plumbing and electrical systems. This is a new process for me and my firm as well as for the owner, which is a long time client of our firm. Please follow this blog as there will be more postings related to that effort coming in the next few months. In the early stages of the design-assist effort, I’m finding it to be a fascinating process, but one where mistakes have already been made.

I'm going to try to keep the names of the owner, A/E and contracting firms and individuals inside those firms confidential. Their names are not germane to the discussion and provide unnecessary information. I have not asked permission to use anyone’s name and we agreed to confidentiality during the collaboration meeting, so I must respect that. With that said, I'm sure anyone who follows design and construction in my area or knows me personally will no doubt be able to figure out who some of these players are, but my purpose is to relay my experiences and thoughts, not point out the mistakes of others. 

It took over a month to organize this collaboration event. Given there were about 30 people invited from a dozen different organizations, finding a suitable date was difficult. The owner and CM finally agreed to hold it on a Tuesday and cancel the regularly scheduled design meetings that would have normally occurred on that day. The owner has given the CM shell space in a building near the construction site for staff office space, so that was the venue for the event.

The moderators of the event were from the home office of the construction manager. This CM is a large, nationally known firm which is headquartered in a major midwest city. These two people apparently run similar collaboration sessions for this CM all across the country. They were incredibly friendly, highly organized and seemed comfortable working with such a large and diverse group of professionals. They were also incredibly focused on the project, the collective team and our needs. They were not trying to make their firm look good but were incredibly focused on making the team better. That was an important thing to happen: adults, especially seasoned construction professionals can see phony a mile off!

The invited parties included several tiers from the ownership team: an Assistant VP, several directors and the owner's project manager and assistant project manager. In attendance from the A/E team was the architect of record's PM and project architect, myself and the principal's in charge for the structural engineer and HVAC, electrical and plumbing engineers. The CM was represented by their project executive, PM and assistant PM. There were also the four design assist contractors, each bringing project executives and one or two other people. On the day of the event, there were 26 people in the meeting plus the two moderators. It was a large group, all from diverse backgrounds and all bringing something different to the table.

I have to question some from the ownership group. The event was scheduled for 9:00A to 4:30P. At the beginning, the lead moderator asked if there were time constraints for anyone in attendance. Due to scheduling conflicts and miscommunication, there was a telecomm and audio-video design meeting in the afternoon. The architect of record’s PM and I had discussed who should attend and ultimately decided this event was too important, so he sent a junior project architect to that meeting. The owner's AVP said he had a conference call at 3:00P but would return for the conclusion of the session. The architect of record’s PM asked to be excused at 4:00P to beat the traffic back to the District of Columbia where his office is located. The moderator said he would work with that. Two people from the owner's team remained silent at this point but left after just one hour of the event. Two others from the owner's team arrived late but did stay for the duration of the event.

In his opening remarks, the owner’s AVP discussed how important he feels this type of event is but was unable to garner the same focus from some on his team. To be fair, many of us have had negative experiences with these types of events which may cause some to be less than interested in attending them. However, the other 22 participants were able to give their attention for a full day, so I believe the entire ownership team should have been able to do so as well. The two individuals who left after one hour were directly involved in one of the issues the group identified and discussed later on in the session.

The printed agenda was somewhat difficult to understand, hence my trepidation before the event started.  However, the agenda proved to be very simple. We introduced ourselves and discussed our experiences with partnering sessions. We then discussed personality or communication styles and took a quiz to help determine our own communication styles. We discussed definitions of each of the four styles and how best to communicate with persons of that style. After lunch, we left the generalities and philosophies behind and focused firmly on our project. I think that was the critical move that made a huge impact on the team and the success of the event.

I have mixed experience with partnering type events. The ones I have attended in the past were not terribly successful. They seem to always start with participants sitting around tables filled with Matchbox Car construction toys: bulldozers, dump trucks, road graders and the like. They seem to focus on heady philosophy or touchy-feely discussions that make professionals uncomfortable. As we began our session, I did not see any construction toys around and we were sitting in a circle so already the mood seemed different. When it came my turn to describe my partnering experiences, I said that I find it insulting to put construction toys in front of construction professionals. That elicited laughs from all and quick agreement from the moderators.

I think I'll save the conversation of the personality styles for a blog by itself, but essentially, this particular personality style indicator focuses on four styles: Producer, Planner, Promoter, Peacekeeper. In our room of 26, there was one Promoter (one of the moderators), one Peacekeeper (HVAC engineer) and the rest of us split between Planner and Producer. One of the characteristics of Planners and Producers is that they sometimes have difficulty communicating with each other as the Planners like to have all information required, in a high level of detail and the Producers want to act quickly, based on just the most important facts. That information by itself probably justified most of the day's expenditure!

As we broke for lunch at this point, I think I’ll break the blog here. Please return in a week or so to learn about the rest of the event. I found it highly successful and I hope the benefits continue to be reaped as the project moves forward.

Tuesday, October 8, 2013

Can a Day Long, Formal Meeting Foster Better Collaboration?

By Marvin Kemp, AIA, CSI, CDT

In about one hour, I'll enter a day long meeting entitled "Building a Highly Collaborative Team." This meeting has been  organized by the construction manager for a large biomedical research building that I am involved in. The meeting will be attended by members of the design team, ownership team, construction management team and design-assist contractors. It will feature a moderator who I'm told is a psychologist. In one day, can this group of individuals build a "highly collaborative team" as the meeting title suggests?

I've attended similar "partnering" sessions before and in one word to answer my own question, no. Typically, these moderators come in with high energy and put construction toys on the tables, play ice breaker games and generally make highly skilled professionals feel childish and like they have wasted an entire day. I hope this one is different, but I'm not sure. The CM's project manager asked my advice and I warned him I against the usual moderator, toys and ice breakers. I think he heard me, but he has to answer to bosses just like I do, so we'll see.

In September of 2011, I posted an article on this blog entitled "A Decent Meal" where I described an end of project luncheon that might should have occurred at the beginning of the project. I suggested to the CM that maybe a long luncheon or barbecue type event might be a better way to foster collaboration. In my view, collaboration starts with familiarity and understanding. There is no better way to get to know people than to share a meal and each other's company. Talking about sports, children or other interests is great way to get to know people and better understand who they are and what they bring to the project team. When we better understand each other, our strengths and weaknesses, we can work better together.

Spending a day in a conference room, feeling like you should be somewhere else might foster resentment and force some to put up their defenses. Important things might be said that aren't heard because of a lack of attention being paid to the meeting. Childish, ice breaker type games are rarely taken seriously by professionals and provide little if  any true understanding of anyone or anything. In construction, we need to understand each other, understand where each of us is coming from, what our motivations are, and work together to reach a common goal.

I'll report back after the meeting with how it went, what we did and other thoughts on building collaboration. Wish me luck and follow me on Twitter @BaltoCSI.